CAPITOL DOME
|
|
|
Thomas U.
Walter's 1859 drawing shows a section
of the dome. Suspended above the eye of the inner dome is Constantino
Brumidi's fresco The Apotheosis of
Washington. The concept of a double
dome with a large painting incorporated between the two segments was
inspired by the dome of the Panthéon, in Paris, which Walter had
visited in 1838.
|
| Examining
the |
|
CAPITOL DOME
|
|
A comprehensive
structural analysis of the United States Capitol's dome reveals that
the dome is sound and capable of resisting all reasonably anticipated
loadings.
|
Eric
C. Stovner, P.E., S.E., Emmanuel E. Velivasakis, PE, Charles H.
Thornton, PE, Glenn G. Thater, and Christopher P. Pinto, I.E.
|
In 1990, Congress
authorized a capital program for the renovation of the dome of the United States
Capitol to address concerns arising from a perceived increase in exterior cracks
and water infiltration. As part of the master plan initiated by Alan M. Hantman,
the architect of the Capitol, to ensure the soundness and longevity of the dome,
LZA Technology, a division of the Thornton-Tomasetti Group, headquartered in New
York City, was commissioned in 1998 to provide structural engineering
consultation services. The primary focus of LZA's work was an analysis of the
dome's structural elements using state-of-the-art computer-assisted techniques
and methods. The analysis was undertaken to assess the structural soundness of
the dome prior to implementation of a four-year, $44-million program devised for
its restoration by Hoffman Architects, headquartered in North Haven,
Connecticut. The Office of the Architect of the Capitol is overseeing the
project.
Construction of the first capitol dome-made of
timber-was begun in 1818, bringing to fruition President George Washington's
intent to crown the Capitol with a grand dome. In the early 1850s Thomas U.
Walter, the fourth architect of the Capitol, was commissioned to design and
supervise the expansion of the U.S. Capitol. In 1855 he proposed replacing the
timber dome with a larger dome that would be in architectural scale with the
expanded building. Because of the preexisting supporting rotunda masonry walls,
the new dome-three times the height of the original dome-would have to be
limited in weight. The designers chose to use cast iron as the primary building
material, an appropriate selection since it can be cast with cutouts or voids in
areas where material is not required for structural purposes. This reduces the
overall weight of the structure. Cast iron also enabled the designers to
customize shapes for the members and provided superior fire resistance. The
castings were constructed within close tolerances, and their quality is
excellent. Interestingly, the total cost of the new iron dome was approximately
the same as that of the smaller timber dome erected 40 years earlier: roughly $1
million.
Construction of the dome began in 1857 under
the supervision of Montgomery Meigs, a military engineer. Although work was
halted at times during the Civil War, President Lincoln-according to some
accounts-made it a point of pride for the Union to complete the dome despite the
ongoing conflict. The 20 ft (6.1 m) tall Statue of Freedom, which caps the dome,
was installed following the dome's completion in 1863.
The dome structure, together with its inner
dome, its outer cupola, most of its outer skin, and its lower skirt, is cast
iron. The boilerplates, tie rods, hangers, and skirt needle beams are wrought
iron. (The skirt needle beams, rolled in 1857, were among the first generation
of I-beam shapes.) From the highest point of the Statue of Freedom-which
commands the top of the dome-to the top of the supporting wall, the dome is
approximately 199 ft (60 m) in height. The diameter of the structure at the base
is approximately 100 ft (30 m). The top of the statue is approximately 290 ft
(88 m) above grade, which compares to St. Paul's in London and St. Isaac's in
St. Petersburg, among the largest domes in the world. The main framing of the
dome consists of 36 meridional arched half-ribs, arranged as inverted
"wishbones" and tied together with circumferential hoop rings. These
ribs transmit loads down to the cylindrical wall of the rotunda, which is
constructed of bonded brick and stone masonry and is approximately 5 ft (1.5 m)
thick. The rib sections-and most of the hoops as well-are trussed with chord
depths of approximately 4 ft (1.2 m). The rib sections are approximately 10 ft
(3 m) tall and spaced at approximately 9 ft (2.7 m) centers toward the bottom of
the dome. The heaviest cast section used in construction weighs approximately 10
tons (9.1 Mg).
 |
| This
historical photo shows the twin-shelled iron dome, which was constructed
between 1857 and 1863, near completion. |
In addition to the main rib framing, elaborate
arrangements of cast-iron members support the inner and outer shells of the dome
and give it its distinctive shape. The inner dome is an ornamental architectural
feature-a coffered, truncated shell-that is hung from the ribs and bracketed at
the peristyle pillars and provides an oculus view up to The Apotheosis of
Washington-Constantino Brumidi's fresco painted as a tribute to George
Washington-on the underside of the canopy, which is hung from the tops of the
ribs. At the top of the dome, the tholos is framed with 12 columns, on top of
which stands the 19.5 ft (5.9 m) Statue of Freedom. The dome elements are bolted
together through cast lugs. At the base of the dome, the colonnade is
approximately 10 ft (3 m) wider than the rotunda wall below-accomplished by
large cantilevering brackets at the top of the wall. The brackets support the
colonnade above and are concealed by a curtain of cast iron, which is referred
to as the skirt.
Structural elements and loading attachments
(hangers et cetera) frame into other elements at common joints and thus form a
trussed, or axial force, system. Local, or secondary, bending occurs within
individual elements (rib sections II to VIII) since such elements are not
completely triangularized within their length. These secondary bending stresses
are small since the nontriangularization occurs within the member length. The
nontriangularization was a designed optimization of material because it entailed
shorter total lengths of cast material.
LZA engineers performed visual condition
surveys of all representative structural component types. The superstructure is
in good condition and exhibits no significant deterioration. Visual observation
of nonstructural elements revealed deterioration of certain elements,
particularly exterior balcony floor plates and balustrade rails, but this does
not affect the overall structural integrity of the dome. Some evidence of
potential distress in the form of cracks in the rotunda masonry walls was
observed, and LZA installed an electronic crack- and temperature-monitoring
system on the walls to evaluate the significance of these cracks.
While a traditional masonry dome is a
three-dimensional continuous structure, an iron-ribbed dome can be accurately
idealized as discrete, linear elements. The manner in which the dome's
structural and attached elements are detailed permits the dome to be modeled
using linear elements. The dome's structural elements are primarily linear truss
members with connectors symmetrical to work points (lines of force action), and
the dome's attached elements-cupola, cladding, canopy, and inner dome-are all
detailed to preclude independent shell behavior.
LZA developed a decision tree and matrix to
select the computer analysis program most suitable for the ribbed truss dome.
Criteria included maximum model size and computing speed, accuracy of matrix
math and effects of internal renumbering of nodes, ease of inputting tapered and
unusual member shape properties, and graphical output capabilities. LZA chose a
prerelease version of LARSA, produced by LARSA, Inc., of New York City, which
uniquely provided most of the desired criteria. Initially the run time for the
model used took three and a half hours on a 300 MHz Pentium II PC with a 256
Mbyte RAM. LZA engineers developed a method implemented by LARSA that optimized
the hardware memory allocation and trimmed the run time to three hours. LARSA
provided support and a first-generation matrix numerical solver technique that
cancels out zeros at unrestrained degrees of freedom and reduces the bandwidth,
resulting in a run time of just seven minutes.
 |
| Thomas U.
Walter's drawing, above, shows a section of the tholos and the Statute
of Freedom. |
LZA created the geometry for the
three-dimensional structural analysis model based on a thorough review of
drawings of the dome executed by its designer, Thomas U. Walter, and site
visits. The analytical computer model includes the bottom of the cast-iron
brackets that bear on the rotunda wall and extends to the top of the tholos at
the underside of the statue pedestal. The model represents the primary
structural elements of the dome, with the exception of the skirt elements that
carry their own weight onto bearing walls below the roof of the Capitol. There
are approximately 7,700 nodes and 16,000 finite- element members in LZA's
structural analysis model.
Nodal geometry for the ribs was developed on
the basis of a drawing by Walter entitled "Demonstration of Main Rib."
This drawing provides dimensions to the interior and exterior edges of the rib
sections. LZA established its nodal geometry by considering the centerlines of
the rib chord cruciform cross sections. These dimensions are appropriate for the
analysis of a trussed rib structure in which primary tension and compression
forces act through the centroids of truss chord members
LZA coordinated with Lucius Pitkin, Inc., of
New York City, for a program of metallurgical testing. Nondestructive in situ
surface replication and hardness tests were performed at various rib sections
and on the boilerplate to characterize the materials and determine their
strength. To determine moduli of elasticity, a coupon sample was cut from a rib
and a sample was cut from the primary boilerplate. Laboratory tests were also
performed on samples of the exterior skin that had been cut for the installation
of drainage piping in 1994.
The cast iron is a gray type, the ribs having a
ferritic microstructure and the exterior skin a pearlitic microstructure. Based
on the hardness tests, the estimated ultimate tensile strength averages
approximately +18 kips per square inch, or ksi, (+124 MPa), which has been
confirmed by the laboratory testing performed on the coupon. The estimated
ultimate compressive strength averages approximately -70 ksi (-483 MPa). Based
on laboratory tensile testing of the boilerplate material, its yield strength
averages +29.5 ksi (+203 MPa) and its ultimate tensile strength averages +46 ksi
(+317 MPa). These strength values correlate with values from 19th-century
material testing as described in engineering texts from the period and testing
performed in 1956. The density of the rib coupon was measured at 430 pounds per
cubic foot, or pcf (6.9 Mg/m3), and the boilerplate sample at 480 pcf (7.7
Mg/m3). These densities are in the typical range for cast iron and wrought iron,
respectively, although 450 pcf (7.2 Mg/m3) is closer to the mean value for cast
iron. The modulus of elasticity, E, was tested, utilizing strain gauges on a
coupon, at an average 10,000 ksi (69,000 MPa) for the cast iron. Though at the
lower range of values for cast iron, this is typical for cast iron of this
strength.
The dead-load self-weight was calculated by the
analysis software using the member areas and material densities input in the
model. Superimposed dead loads-such as the inner dome and the exterior skin
plates-were calculated from information in the Walter drawings. Dead loads were
calculated within close range of the historically published weight of the dome,
8,909,200 lb of iron (4,041,213 kg). An interesting conclusion from the
calculation of dead loads is that the percentage of material volume or weight
devoted to the superstructure is approximately the same as that devoted to
nonstructural elements. In comparison, modern steel-framed structures typically
weigh less than a fifth as much as the building elements they support.
Various live loads are possible; the governing
live-load condition consists in a buildup of ice on the exterior surface during
a cold storm. A distributed live load from a half-inch (12.7 mm) layer of ice
was utilized with two cases considered: ice buildup on the entire dome surface
and an unbalanced load condition of ice on only half of the dome. The weight of
a half-inch (12.7 mm) layer of ice on the entire dome surface is 122,000 LB
(55.3 Mg).
Wind loads were calculated in accordance with
the principles and climatological velocity and gust response factors set by
Building Officials and Code Administrators International (BOCA) and ASCE 7-93
(Minimum Design Loads for Buildings and Other Structures), utilizing the 80 mph
(129 km/h) design wind speed specified in the building code for Washington,
D.C., with wind pressures applied perpendicular to every rib. The external
pressure coefficients appropriate for a large-diameter cylindrical structure
such as the dome were derived from research performed for cooling tower
structures. The magnitudes of the peak coefficients result in wind pressure,
which correlate with magnitudes for conventional buildings calculated to include
internal wind pressure.
Because the structural elements of the dome are
attached and supported with restraint and are not thermally isolated, changes in
temperature will induce stresses in the structure as it expands or contracts.
The average daily temperature in Washington is approximately 56°F (13.3°C),
the highest temperature ever recorded being 106°F (41.1°C) and the lowest -15°F
(26.1°C). Assuming the dome was built during a period of average temperature,
the maximum changes in temperature that the dome has been subjected to are a
positive 50°F (27.8°C) change and a negative 71°F (39.4°C) change. Such
thermal differentials were applied as loads to the entire analysis model, and
unbalanced thermal loading conditions were also considered.
|
|
This view
from the
rotunda
floor of
the inner
dome shows Brumidi's
Apotheosis.
|
According to the Washington, DC, building code,
the District of Columbia is in seismic zone 0-that is, low hazard, with Av (the
effective peak velocity-related acceleration coefficient) equal to 0.05. The
current analysis treats the dome as an element of a structure. Per the Uniform
Building Code, this treatment implicitly considers an element as having low
ductility. Cast iron is brittle; however, the dome has other characteristics
that are beneficial for seismic performance: compact members, redundancy, high
factors of safety, and quality in construction. The dome element design lateral
force was distributed vertically in a way that is inversely proportional to the
mass of the dome, similar to Uniform Building Code requirements for the design
and analysis of entire buildings, to represent modal amplification effects. The
lateral loads were applied at hoop levels, which are essentially the structural
diaphragms of the dome.
The various potential load combinations were
scrutinized to determine the governing stress condition in the structure. Load
combinations were factored in accordance with ASCE 7-93.
All members of the structural analysis model
were reviewed for the worst-case stress condition for all load combinations. The
vertical reactions for dead plus superimposed dead (service) loads sum to 8.4
million LB (3.8 million kg), which is equivalent to the weight of the dome minus
the skirt. As the gravity loads increase toward the bottom of the dome, the ribs
increase in cross-sectional size. However, the compression stresses generally
increase gradually in the ribs toward the bottom. Stresses range from 0 to -4
ksi (0 to -27.6 MPa).
The maximum horizontal reaction at each rib
pillar from gravity loads is about 3 kips (1.36 Mg) and is radially outward
(perpendicular to the rotunda wall). Thus, the horizontal reactions exert an
inward force at the top of the rotunda wall. Approximately 40 ft (12.2 m) above
is the spring line-or the bottom of the arched portion of the ribs-at which the
dome tends to thrust outward. A pivoting or double curvature made possible by
the flexibility of the tall peristyle pillar construction changes the direction
of the horizontal reactions and delivers these reactions inward at the top of
the rotunda wall. This is a brilliant redirection of structural forces.
Presumably, this was considered by Walter's chief assistant, August G.
Schoenborn, who conceived the structural form of the rib and peristyle framing.
The rotunda masonry bearing wall, cylindrical in plan, cantilevers above the
Capitol's fourth, or attic, floor level. Inward horizontal reactions deriving
from gravity loads are ideally suited for the cantilevered unreinforced masonry
bearing wall because the cylinder behaves as a compression ring.
 |
| There are
approximately 7,700 nodes and 16,000 finite-element members in LZA
Technology's structural analysis model, shown here in isometric view. |
The first hoop from the top that undergoes
tension in response to dead and superimposed dead loads is the hoop between
sections III and IV. The hoops of solid wrought iron plate have higher forces
than the hoops of rigid cross bracing because of the increased areas and
stiffnesses of the plates.
The hoop boilerplate at the top of section VIII
has maximum compression stresses of -2.2 ksi (-15.2 MPa). A gradual transition
of stress levels occurs in the intermediate hoops, with the exception of the
boilerplate hoop between sections V and VI, which draws more load than the cross
bracing in the hoops at the levels immediately above and below. Displacements
are well within generally acceptable limits. The maximum vertical deflection of
the dome under dead plus live loads is less than 1/4 in. (6.4 mm).
From lateral loading, the maximum tension
stress in the tie rod bracing members that occur between ribs is +7 ksi (+48.3
MPa). Rib and hoop stresses range from 0 to +4 ksi (+27.6 MPa).
The maximum deflection from lateral load is
about 1 in. (25 mm) and occurs at the tholos level. Expressed as a ratio to the
height of the dome, the lateral deflection is 1/2,500 of the height. Because of
the magnitude of dead loads, the dome is not subject to uplift for design
lateral loads. .
Load combinations involving peak thermal loads
tend to be the governing load combinations for the rib section chord members.
Thermal forces increase toward the bottom of the dome and become larger in rib
sections II and III. Hoop forces arising from thermal loads are moderate. The
largest deformations occur during peak thermal loadings. The largest vertical
deflection, about 1 in. (25 mm) downward, occurs in the tholos area and is due
to combined dead loads and negative differential thermal loads. The largest
lateral deflection, about 1.5 in. (38 mm), occurs near the top of the tholos and
is due to combined dead loads and unbalanced positive differential thermal
loads. Plots of the crack displacement and temperature test data show a clear
and distinct pattern; that is, as the temperature increases the cracks decrease
in size and as the temperature decreases the cracks increase in size. Positive
thermal loading on the structure causes the cast iron to expand and results in
an outward force being applied to the top of the rotunda walls. The
approximately 5 ft (1.5 m) thick masonry walls move outward slightly as the
thermal loading increases. The movement, although very small, is greatest at the
top of the wall and decreases toward the bottom. This movement will tend to
close horizontal or diagonal cracks on the exterior face of the wall as the
thermal loading increases. The cracks' average movement is 2/1,000 to 3/1,000
in. (51 to 76 µm) per 10°F (5.56°C) change in temperature.
The recent metallurgical testing substantiated
the notion that the ultimate stresses of the dome elements are typical of
expected strengths. LZA consulted engineering texts of the 19th century
containing descriptions of material testing and calculated or utilized the
appropriate factors of safety required to determine suitable allowable stresses.
LZA further reviewed the stability characteristics of the dome compression
elements. The unstiffened projecting elements, or flanges, typical of the rib
and hoop cross-sectional cruciform shapes are sufficiently stout that the
allowable compression stresses are not reduced for local buckling
considerations. The rib and hoop unbraced lengths were considered by calculating
the Euler buckling load of each compression element. For example, the allowable
compression stress at the inner chord of rib section V is reduced from -12 ksi
(-82.7 MPa) allowable crushing stress to a governing -7 ksi (-48.3 MPa)
allowable compression stress caused by buckling. Calculations of the allowable
buckling stresses reveal further optimized design: rib sections toward the
bottom and hoops toward the top (those members receiving the highest compression
forces) are the members with the greatest stoutness.
Defining the factor of safety as the ratio of
ultimate failure load to allowable load provides a factor of safety of 6 for the
cast iron and a factor of safety of 4 for the wrought iron. For all load
combinations, all members are within allowable stresses. Evaluation of the rib
and hoop member stresses reveals that approximately 80 percent of the structural
members are stressed to less than +3 ksi (+20.7 MPa).
For the wrought iron boilerplates, the maximum
tensile stress is in the primary boilerplate at the spring line. The maximum
tensile stress is +2.4 ksi (+16.5 MPa), which is well within the allowable
tensile stress of +12 ksi (+82.7 MPa). The boilerplate between sections V and VI
undergoes compression with a maximum stress of -2.5 ksi (-17.2 MPa), which is
within the allowable stress taking into account the buckling strength. Shear
stresses were reviewed and found to be minimal, approximately 360 psi (2.48 MPa)
maximum. Such stress values are acceptable, since allowable shear stresses are
approximately 3 ksi (20.7 MPa) and 12 ksi (82.7 MPa) for cast and wrought iron,
respectively.
During a 1956 analysis conducted by the
engineering firm Seeley, Stevenson, Value, and Knecht (SSVK), of New York City,
significant deterioration was observed in the primary boilerplate upon removal
of moldings at the joint between the exterior first-story deck plates and the
exterior vertical dome plates. SSVK measured a loss of 25 percent of boilerplate
material. As a result, two posttensioned cables were added at the boilerplate
level. LZA's three-dimensional analysis indicates that the cables reduce the
boilerplate stresses by 600 psi (4.1 MPa), or approximately one-third of the
original stresses in the boilerplate. In terms of the magnitude of stress, the
loss of material found by SSVK is insignificant, as the ratio of the actual
tensile stress to the allowable tensile stress is 20 percent, or if corrected
for locations suffering 25 percent deterioration, a stress ratio of 27 percent.
The structural elements of the dome are within
their allowable stresses for all applicable loadings. The dome of the United
States Capitol is a crowning achievement in the technology of cast iron.
Castings were constructed within close tolerances. The quality of the structural
castings is excellent. In terms of structural and construction design, the dome
is a testament to the talents of scientifically trained minds. The optimization
of structural members and the levels of structural redundancy support a
structure that is sound and capable of resisting all reasonably anticipated
loadings. Thomas U. Walter's accomplishment was a masterful one.
Eric C. Stovner, PE, SE,
M.ASCE, is an associate with LZA Technology in Tustin, California. Emmanuel E.
Velivasakis, PE, F.ASCE, is a senior vice president, Charles H. Thornton, Ph.D.,
PE, Hon.M.ASCE, the chairman, Glenn G. Thater a project director, and
Christopher I. Pinto, I.E., A.M.ASCE, a senior engineer with LZA Technology in
New York.
|
|
|
Sourcce:CIVIL
ENGINEERING MAGAZINE, October 2000
|
|
|
|
|
|