|
|
|
A
Grand New Bridge
|
|
The
Seohae Grand Bridge, South Korea's longest
crossing, features a
470 m center span that is the longest in the
country.
|
|
|
At
9.4 km, the Seohae Grand Bridge now stands as the longest
bridge in South Korea. Rising above the Asan Bay
approximately 65 km south of Seoul, the cable-stayed bridge,
which took seven years to construct, runs from P'y_ongt'aek
on the north side of the bay to Dangjin on the south. The
bridge incorporates pistonlike lock-up devices (LUDs) that
allow movement in response to temperature changes, creep,
and shrinkage but resist such dynamic loads as aerodynamic
motions and earthquakes. These devices are of critical
importance, because a primary design challenge for the
Seohae Grand Bridge was its location in an area of high
winds.
 |
|
Four travelers
formed the bridge deck, left. The main bridge,
previous page, comprises the double cable-stayed
structure and two side spans.
|
The crossing consists of
several kilometers of concrete box girder spans and the main
bridge, which is 990 m long. The main bridge consists of an
870 m long cable-stayed structure and two 60 m long end
spans of simply supported composite girders. The
cable-stayed portion has three spans-a 470 m center span and
two 200 m side spans. The center span provides a 62 m high
navigation channel above the bay.
There are six traffic
lanes, three in each direction. Together with a 3 m outside
shoulder, a 1.2 m inside shoulder, and a 0.8 m median
barrier, the roadway width between the inside faces of the
outside barriers is 31 m. The centerlines of the cables are
placed at a distance of 1.6 m from the inside face of the
outside barrier, making the center-to-center distance
between the two planes of cables 34 m.
T.Y. Lin International, of
San Francisco, performed the detailed design of the main
bridge and also provided construction services, including
superstructure erection stage analysis, design of special
construction equipment, and field assistance.
The 60 m end spans of the
bridge (from piers 39 to 40 and piers 41 to 42) are
connected to the cable-stayed spans by a hinge at piers 40
and 41. In this way the rotations in both the 60 m span and
the cable-stayed spans will be kept independent (see figure
1). However, the hinge connection does not allow relative
movement longitudinally.
Large expansion joints
placed at the transition between the end spans and the
approach spans accommodate the total longitudinal movement
of the entire main span. In that location they will
facilitate the periodic replacement that is necessary with
expansion joints that permit large movements. Placing the
joints at the end anchorage zone of the cable-stayed spans
would have been less than optimal because that area is, in
itself, very complex structurally.
Elastomeric bearings placed
under the edge girders at the bridge's two pylons restrain
the deck girder in the transverse direction, while lateral
bumpers located at the edge of the edge girders further
restrain the maximum relative transverse movement between
the girder and the pylons. The vertical bearings are sized
to provide approximately the same stiffness as the adjacent
cables, so the girder behaves more like a floating member.
This allowed the design to do without a hard point support,
which would have caused a very high bending moment in this
area of the girder.
To control the bridge's
longitudinal displacements under live loads and other
dynamic loading while allowing creep, shrinkage, and
movement in response to temperature changes, the girder is
hinged at one pylon and is movable at the other. However, to
activate the horizontal support of the latter pylon under
such dynamic loads as aerodynamic motions and earthquakes,
LUDs are installed to connect it to the girder. The LUDs
allow slow motions to take place but they lock up, or
freeze, under quick motions. Accordingly, the structural
system responds differently to static and dynamic loads.
The LUD is essentially a
piston. Normal pistons, for example, those in a steam
engine, have one valve at each end so that the piston can be
pushed back and forth depending on which opening the steam
is coming through. An LUD, by contrast, is a piston with no
holes at either end. Instead, there are holes in the piston
itself. The cylinder, which is filled with a viscous liquid,
can move slowly in response to such forces as creep and
temperature expansion because the liquid can flow from one
side of the piston to the other through the holes. But when
forces act on the bridge quickly, the piston is frozen
because the small holes do not allow the liquid to flow
quickly enough. By adjusting the viscosity of the liquid and
the size of the holes, the LUD can be "tuned" to
various degrees of fixity.
The deck of the Seohae
Grand Bridge consists of two longitudinal steel girders
spaced 34 m apart, with steel floor beams 4.10 m apart
running transversely between these edge girders. The roadway
deck consists of precast-concrete panels, the edges of which
are all 310 mm deep, and cast-in-place joints. In the
vicinity of the pylons, where the axial compression of the
girder is high, the slab panels are solid. The panels have
the shape of an inverted bathtub and are 260 mm thick in the
area closer to midspan, where the axial compression is
smaller. The thickness increases to a uniform 310 mm within
five cable spaces on either side of the pylons to carry the
increased axial compression force. Since the cast-in-place
gaps are always placed on top of a steel beam, forming was
not required.
Transverse and longitudinal
deck posttensioning addressed the shear lag effect at the
center and at the end of the bridge by creating the
necessary compressive stresses to bring the anticipated
tensile stress within acceptable limits. The multistrand
tendons, each comprising four strands 15.2 mm in diameter,
were used for the longitudinal prestressing of the deck. The
tendons were posttensioned after the closure segments have
been completed.
Edge girders, a steel
stringer located in the center of the roadway, and the floor
beams support the precast panels. The gap between the
panels-which were filled with nonshrinking concrete after
being placed-is 420 mm on top of the floor beams and 500 mm
on top of the stringer. At the edge girder, a thickened
cast-in-place slab of nonshrinking concrete extends the
panels. Shear studs transfer the shear force between the
steel girders and the concrete slab, and a large number of
reinforcing bars-extended from the precast panel into the
gaps-ensure continuity of the slab, which is designed as a
continuous plate over elastic supports.
The edge girders are mostly
under compression. In regions where the bottom flange will
experience tension, the vertical stiffeners are bolted to
the bottom flange to avoid fatigue problems. The web of the
edge girders is 2.80 m deep. The bottom flange is 50 mm
thick, except at the end segments, where it increases to 60
mm. The width of the bottom flange varies from 860 to 920
mm. The top flange, which is typically 500 by 50 mm, is
located only on the inside face of the web to accommodate
the cable anchorage. Because the cable anchorage plate is
bolted directly to the outside face of the web, the local
bending moment caused by the eccentricity of the anchorage
from the centerline of the web (which usually exists in such
cable connections) was virtually eliminated.
The side spans of the
bridge are 200 m long, which is less than half the length of
the 470 m long center span. Several cables are grouped
together at the ends of the side spans above each anchor
pier, where the edge girders deepen to 5 m to accommodate
the cable anchorages and to provide room for the large end
girder, which supports the steel girders from the end spans.
|
|
|
Two planes of 72
cables fan out from the tops of the pylons. Each
cable
contains 37 to 91 galvanized, wax-coated strands.
|
The steel floor beams run
perpendicular to the two edge girders. The web is 2.8 m deep
at the center, decreases to 2.5 m following the slope of the
deck, and then increases again to the same depth as the edge
girder. The top flange of the floor beam is 600 mm wide to
provide sufficient room for the support of the precast-concrete
panels and to allow for a large gap between the panels so
that reinforcing bars can be properly spliced.
The floor beams were
designed to carry the full structural dead load as a simple
beam, without help from the concrete slab. During
construction, however, four inverted king posts, one at each
of the four front floor beams, were used to apply a
predetermined load, thereby bending the floor beams before
the gaps between the precast panels were poured and
achieving a certain amount of residual compression in the
top slab to reduce the possibility of cracking. This
approach also allows repair of the top slab without any
temporary support.
The concrete end floor
beam, which weighs approximately 1,300 Mg, was precast on
the ground and then lifted into place by means of a giant
floating crane. The weight of the end beam, together with
the reaction from the end span, is sufficient to overcome
any uplift reaction under service loads. The end beam is
structurally connected at each end to the steel edge girders
by transverse posttensioning, which is anchored on the
outside faces of the edge girder webs. Additional short
tendons provide more capacity to transfer the vertical and
horizontal shear forces between the edge girders and the
deck slab at the end region.
Rising 180 m from the base,
the Seohae Grand Bridge's pylons consist of two hollow
rectangular columns, with exterior dimensions varying from
15.7 m at the base to 6.6 m at the top of tower in the
direction of the roadway (see figure 2). Perpendicular to
the direction of travel the column dimensions range from 6 m
(below the deck) to 4 m (above the deck). As a rule, the
columns are poured in 4 m segments, although smaller
pours-down to about 2 m-are used above the upper crossbeam
where the stay-cable anchorages are located.
The bridge's two upper
crossbeams were selected for aesthetic reasons by the owner.
The upper portions of the pylon columns are vertical and
spaced at the same distance as the cables so that all cables
are vertical in the longitudinal view. Since the vertical
curve of the roadway is not exactly symmetrical with the
main span, the two pylons have slightly different heights.
The difference, however, is barely noticeable.
Slip forming was used to
simplify construction of the pylons. The lower crossbeam was
precast on the ground and lifted to its final elevation by
strand jacks attached to the pylon legs. The reinforcing
bars at the ends of the crossbeam are coupled to the bars
embedded in the pylon legs and the gaps are then filled in
to monolithically connect the lower crossbeam to the pylon
legs. The lower of the two upper crossbeams, formed and cast
on top of the lower crossbeam and then lifted into place
with strand jacks, was made monolithic in the same way.
After the lower crossbeam was complete, supports were
constructed on top of it, and formwork was constructed on
top of these supports. The upper crossbeam was then cast on
this formwork.
 |
| The pier table
was assembled on the ground and lifted into place by
a large-capacity floating crane. |
Like the pylon crossbeams,
the pier table, consisting of the steel frame and the
cast-in-place deck slab, was fabricated on the ground. After
the lower crossbeam was completed and while the upper
portion of the tower was under construction, a large barge
crane lifted the pier table panel to its final position. The
large-capacity crane saved time and made erecting the pier
table much simpler.
Hammerhead-shaped anchor
piers support the cable-stay bridge end beam, and the 60 m
end span girders are supported by hinge bearings on the end
floor beam. Two 37-strand tie-downs hold the end beam to the
pier to ensure stability of the cable-stayed bridge during
construction. They also act to provide stability in the
unlikely event that the 60 m side span is separated from the
rest of the bridge as a result of an accident or is removed
for a retrofit or replacement. During service loads, the
anchor piers are always under compression.
Dual-plane stay cables
support the bridge, fanning from the top of the pylons and
anchored to the steel edge girders. There are 72 cables in
each cable plane, ranging in size from 37 to 91 strands,
each 15 mm in diameter, a system supplied by Freyssinet, of
Saint-Rémy-de-Provence, France. The strands are galvanized,
covered with wax, individually sheathed, and then placed
inside a plastic pipe without grout. The external pipe has a
rib spirally wound around the outside face to improve the
aerodynamic behavior of the cables.
To stress each strand
individually, Freyssinet's Iso-tension method-which
incorporates a monostrand jack-was used. A load cell mounted
to the first stressed strand indicates the appropriate
tensioning force in each subsequent strand. The stay cables,
which are designed to be replaceable in traffic, are
stressed from the upper end inside the pylons, where the
cable concentration makes the process more efficient. The
nonjacking ends of the cable anchorages are conveniently
located above the deck. This eliminates the need for special
platforms for regular cable inspection. At the lower end,
the cable is anchored into a steel plate, which is attached
to the girder web by high-strength, friction-type bolts to
avoid fatigue problems caused by welding.
 |
| The
lower of two upper crossbeams was cast on a lower
crossbeam and lifted into place by strand jacks. |
After the steel frame of
the superstructure's end segments was assembled at the site,
the 1,700 Mg end concrete floor beam was formed and poured,
posttensioned, and then lifted to its final position on top
of the end piers by means of the same barge crane used to
lift the pier table segments. The steel frame of each panel
consists of three 34 m long floor beams connected to 12.3 m
long edge girders. Four custom lifters, one at the end of
each cantilever, lifted the steel frame of each panel from a
barge to its final position. After the edge girders were
aligned and bolted to the cantilever, the same lifter raised
the precast panels, one at a time, and placed them on top of
the steel frame. The gaps between the panels were filled
with nonshrinking concrete.
The erection of the steel
girders in the two halves of the bridge proceeded
simultaneously, and cable forces were adjusted as new
segments are erected to ensure that the deck tension remains
close to zero. To allow easy placement of the final, 12.3 m
long closure segment, half the girder was moved backward
about 30 cm by hydraulic jacks. The last steel frame panel
was then lifted and the splice bolted together before the
girder was jacked back and the final splice bolted.
With the last steel frame
in place, the space between the two middle floor beams was
not sufficient to allow the lifting of the deck panels, so
the last floor beam was dismantled to provide the required
space. This floor beam was reinstalled after lifting of the
precast panels, which were temporarily stored on the
finished portion of the deck. After completing the erection
of the girder, a detailed survey of the bridge was made and
the cable forces were adjusted according to predetermined
values.
Construction of the pylons
began in mid-1998 after completion of the cofferdams and the
solid-footing foundation. The bridge superstructure was
opened to traffic in November 2000.
Man-Chung
Tang, PE, is the chairman of the board and the technical
director of T.Y. Lin International, San Francisco.
Project
Credits
Owner's representative: Chan-Ming Park, Korean Highway
Corporation, Seoul, South Korea
Contractor's representatives: Tae-Sup Yoon, Seo-Kyung Cho,
and Jong-Gyon Paik, Daelim Industries, Seoul, South Korea
Design: Man-Chung Tang, Gloria Hwang, and Dennis Jang, T.Y.
Lin International, San Francisco; Dennis Lee, Leedco
Engineering, Los Angeles
Design review: M.R. Huh and J. Son, Byucksan Engineering,
Seoul, South Korea
Aerodynamics: Robert Scanlan and Nick Jones, Johns Hopkins
University; Jon Raggert, West Wind Laboratory, Carmel,
California
Construction engineering: Man-Chung Tang, Dennis Jang, J.R.
Tao, and Mark Chan, T.Y. Lin International
Construction site support: Kook-Joon Ahn, T.Y. Lin
International; Erich Aigner, Leedco Engineering
Construction inspection: Daewoo Engineering and COWI Consul,
Copenhagen, Denmark
Source: CIVIL ENGINEERING MAGAZINE, February 2001
|